This project will develop and organize a first- stage civic infrastructure pilot in Kanabec County, within the membership of the PICKM (Pine, Isanti, Chisago, Kanabec, and Mille-Lacs) Alliance, and with other organizations in the St. Croix Basin. The work will be grounded in the need for sustainable citizen engagement in water quality management. Civic leaders participating in this project will build their own skills for organizing people and working in partnership with Kanabec County SWCD staff and the St. Croix Basin Team to achieve water quality goals.
The MPCA, in partnership with the Vermillion River Watershed Joint Powers Organization, contracted with Wenck Associates, Inc., to develop the Stressor Identification (SID) Report; and develop the necessary models for the Vermillion River Watershed Restoration and Protection Strategies (WRAPS) as part of Phase I. The final Vermillion River Watershed SID report discusses all of the analysis that was done in the watershed to identify the primary stressors causing the fish and macroinvertebrate impairments in the watershed.
The Snake River Watershed Management Board (SRWMB), working in concert with other local governmental units in within the watershed, will assist the MPCA, the project consultant, and other members of the Snake River Watershed Total Maximum Daily Load (TMDL) technical team in the completion of tasks associated with this TMDL project. SRWMB, with assistance from members of the technical team (Kanabec Soil and Water Conservation District (SWCD), Pine SWCD, Aitkin SWCD, and Mille Lacs SWCD) will provide the services to complete this TMDL project.
TMDL project in the Chisago Lakes Lake Improvement District that will develop a watershed based plan and provide strategies for water quality and aquatic ecosystem management, restoration, and protection within Sunrise River Watershed. This project will also aid in understanding the Phosphorus loading to Lake St. Croix.
This project will provide baseline data through water monitoring, recording and analyzing the results of six unassessed rivers/tributaries, three unassessed lakes and five storm water outlets in the city of Mora which drain to the Snake River; promote and implement approved BMP’s.
This project will continue the offering of low-interest loans to citizens, some of whom may not be able to acquire funding otherwise, for upgrading 50 septic systems to ensure compliance with state rules. Grant funds will be used to administer the low-interest loan program.
Implementation activities proposed as a part of this project include water quality monitoring, biotic surveys, sediment core sampling, mechanical treatment of curly-leaf pondweed (in accordance with regulations and permitting), an iron-enhanced sand filter, with a high capacity multi-stage outlet weir and 40,000 pounds of iron filings and stakeholder involvement in the design process and educational presentations.
The acqusition of this 80 acre parcel is a very nice fit to the Dalbo WMA. It allows for expanded habitat management and hunting opportunities for a myirad of wildlife species. This is a wonderful additon/round-out to this expansive and heavily used WMA. Which currently is 2610 acres in size.
This MDHA chapter provided significant dollars to help DNR acquire 460 tract with in the past two years.
This project determines ambient background per- and polyfluoroalkyl substance (PFAS) levels in urban and non-urban soils. This information will help Minnesota develop management strategies for PFAS contaminated soils.
To provide an educational overview of Isanti County over the five days of the Isanti County Fair. "Discovering Living History at the 135th Isanti County Fair" will provide visitors with an authentic, historically accurate old west experience, opportunity to hear live bluegrass music and interact with German folk musicians, and wander through exhibits showcasing artifacts of Minnesota's past.
We will determine the distribution, relative density, and spatial occupancy patterns of 3 small weasel species in Minnesota to fill key knowledge gaps in weasel distribution and status in Minnesota.
This feasibility study will produce strategies for wetland restoration and ditch hydrology changes to reduce the amount of phosphorus and solids that drain into Typo and Martin Lakes, the Sunrise River and St. Croix River. Total Maximum Daily Loads and other plans have identified this area as key for pollutant reduction, and the study will determine scope and effects of potential projects, allowing the district to prioritize those that will have the great impact on water quality.
We restored and enhanced a total of 40,539 grassland acres with 446 activities on Wildlife Management Areas, Scientific and Natural Areas, Native Prairie Bank easements, Waterfowl Production Areas, and National Wildlife Refuges.
Minnesota's iconic northern forest habitats, along with their interlaced wetlands and brushlands, are in need of management for the future due to stressors such as invasive species and climate change. This request will enhance and restore up to 3,250 acres of habitat in the Northern Forest Region on WMAs, AMAs, State Forests, and SNAs to increase forest health and resilience, and ultimately wildlife populations, through activities of a roving crew over three years.
Grasslands continue to be the most threatened habitat in the state. This programmatic request will build on the DNR's history of enhancing and restoring grasslands, embedded wetlands, and savannas to increase wildlife populations. The Prairie Plan, Pheasant Plan, and Wildlife Action Plan will guide our efforts and ensure we are operating in a strategic and targeted manner. This proposal will enhance and restore grasslands on parcels that are permanently protected and most open to public hunting.
This project supports continuing development of County Groundwater Atlases for approximately three years. The goal is to provide this valuable water and resource management information infrastructure to every county.
With this appropriation, the DNR enhanced and restored over 11,700 acres of public lands or permanently protected private lands under easement. Projects under this appropriation included prescribed fire, prescribed or conservation grazing, woody removal, and enhancing plant diversity. With this appropriation we were able to exceed our target acreage by 38 percent.
DNR modified six dams to allow fish passage and enhanced in stream habitat on two rivers with this appropriation. Also, habitat enhancement project were completed on 28 Aquatic Management Areas and three metro parks, totaling 1,002 acres. Stream habitat work for this appropriation and LSOHC-funded projects from other appropriations was aided by funding for a stream restoration coordinator and interns. These positions aided in public outreach, survey work, design, permitting, contracting, and coordination with project partners on these complex projects.
We will use a programmatic approach to achieve prioritized aquatic habitat protection, restoration, and enhancement of lakes and streams across all the LSOHC planning regions of Minnesota.
Minnesota's iconic northern forests, wetlands, and brushland habitats require management beyond basic forestry practices or at smaller scales than commercial operations work. Other enhancements, such as brushland shearing or mowing have low commercial value but high wildlife value. These additional habitat enhancements improve the quality of the forests for both wildlife and outdoor recreation.
Grasslands continue to be the most threatened habitat in the state. This programmatic request will build on the DNR's history of enhancing and restoring grasslands, embedded wetlands, and oak savannas to increase wildlife populations. The Prairie Plan, Pheasant Plan, and Wildlife Action Plan will guide our efforts to ensure we are operating in a strategic and targeted manner.
Acquire approximately 230 acres of high priority habitat for designation as Wildlife Management Area or Scientific and Natural Area in the LSOHC Prairie, Forest/Prairie Transition, and Northern Forest Planning Sections emphasizing Minnesota Prairie Conservation Plan, Conservation That Works, 3.0 WMA and AMA Acquisition & Management Strategic Plan and, SNA Strategic Land Protection Plan with priority given to sites of high and outstanding biodiversity significance by the Minnesota Biological Survey.
The Minnesota Department of Natural Resources (MNDNR) will complete six fish passage projects to reconnect reaches of habitat for fish and other aquatic life, restore 71 acres on eight rivers to create over six miles of diverse habitat, and enhance 224 acres of riparian and terrestrial habitat on Aquatic Management Areas. The footprint of fish passage projects is small, but projects will reconnect over 290,000 acres of lake and river habitat.
Minnesota's iconic forests and brushland habitats require enhancement beyond DNR timber harvest practices. Enhancements, such as brushland shearing provide critical wildlife habitat but are not achieved through timber harvest practices. These additional habitat benefits improve the quality of the forests for wildlife, water quality and outdoor recreation. DNR's Conservation Agenda, Wildlife Action Plan, Forest Action Plan, SNA Strategic Land Protection, Fish Habitat Plan, will guide habitat enhancements in this proposal to meet the objectives put forth in these plans.
This DNR Aquatic Habitat appropriation used a programmatic approach to achieve prioritized aquatic habitat restoration, and enhancement of lakes and streams across all the LSOHC planning regions. Two large stream restoration projects totaling 54 acres were completed with this appropriation. Also, habitat enhancement projects were completed on 51 Aquatic Management Areas, totaling 1252 acres. Stream habitat work for this appropriation and LSOHC-funded projects from other appropriations was aided by funding for a stream restoration coordinator and interns.
This DNR Aquatic Habitat appropriation used a programmatic approach to achieve prioritized aquatic habitat restoration, and enhancement of lakes and streams across all the LSOHC planning regions. Two stream restoration projects totaling 23 acres were completed with this appropriation. Also, habitat enhancement projects were completed on 43 Aquatic Management Areas, totaling 849 acres. Stream habitat work for this appropriation and LSOHC-funded projects from other appropriations was aided by funding for a stream restoration coordinator and interns.
We restored and enhanced a total of 15,577 grassland acres with 239 projects on Wildlife Management Areas, Scientific and Natural Areas, and Native Prairie Bank easements.