Vadnais-Snail Lakes Flood Redesign and Reconstruction
Re-design and reconstruct park features and trail routes in Vadnais-Snail Lakes Regional Park. Redevelop the beach area so it is useful with water at varying elevations; improve the beach building; add/improve pedestrian connections, parking, site amenities, signage, stormwater and landscaping
Vadnais-Snail Lakes Regional Park
Sec. 4 METROPOLITAN COUNCIL $19,819,000 $20,277,000
Completed improvement projects. Monitor the number of days the beach and trails are open each year in all weather conditions. Compare precipitation amounts to years when facilities were closed. Complete design; beach are redevelopment; building redevelopment; pedestrian connections; parking; site amenities; signage; stormwater and landscaping
Completed improvements consisted of 21,000 sq ft of new beach, replaced and repaired 2,734 sq ft of existing beach, 434 linear feet of beach curbing, 900 sq ft of improved ADA access with curb ramp