Trail construction at Spring Lake Regional Park

Project Details by Fiscal Year
2016 Fiscal Year Funding Amount
$300,000
Fund Source
Parks & Trails Fund
Recipient
Scott County
Status
Completed
Start Date
July 2015
End Date
June 2018
Counties Affected
Scott
Scott
Project Overview

Construct segment of planned trail system and implement natural resource wetland restoration and enhancement work in collaboration with the Shakopee Mdewakanton Sioux Community, City of Prior Lake, and the Prior Lake-Spring Lake Watershed District. This project will leverage funds from partner agencies.

Project Details

Spring Lake Regional park

Legal Citation / Subdivision
M.L. 2015, Chp. 2, Art. 3, Sec. 4 (SFY 2016) PTLF
Appropriation Language

Sec. 4. METROPOLITAN COUNCIL$17,237,000$18,067,000
(a) $17,237,000 the first year and $18,067,000 the second year are for distribution according to Minnesota Statutes, section 85.53, subdivision 3.
(b) Money appropriated under this section and distributed to implementing agencies must be used to fund the list of recommended projects in the report submitted pursuant to Laws 2013, chapter 137, article 3, section 4, paragraph (o). Projects funded by the money appropriated under this section must be substantially consistent with the project descriptions and dollar amounts in the report. Any funds remaining after completion of the listed projects may be spent by the implementing agencies on projects to support parks and trails.
(c) Grant agreements entered into by the Metropolitan Council and recipients of money appropriated under this section must ensure that the funds are used to supplement and not substitute for traditional sources of funding.
(d) The implementing agencies receiving appropriations under this section shall give consideration to contracting with Conservation Corps Minnesota for restoration, maintenance, and other activities.

2016 Fiscal Year Funding Amount
$300,000
Proposed Measurable Outcome(s)

1. Lineal feet of trail constructed across berm through wetland providing access to and observation of public ally owned wetlands and an iron-sand filter system for water quality treatment installed by project partners. 2. Trail miles constructed. 3. Num

Measurable Outcome(s)

Project completed 475 lineal feet of trail constructed across berm through wetland, 0.64 miles of trail constructed, and 4 partners involved in successful trail construction including Shakopee Mdewakanton Sioux Community, Prior Lake Spring Lake Watershed District, City of Prior Lake, Three Rivers Park District.

Recipient Board Members
County Board
Project Manager
First Name
Patricia
Last Name
Freeman
Street Address
200 4th Ave W
City
Shakopee
State
MN
Zip Code
55379
Phone
952-496-8752
Email
pfreeman@co.scott.mn.us
Administered By
Administered by
Location

390 N. Robert Street
St. Paul, MN 55101

Phone
651-602-1000