Reconstruct Chamonix golf course clubhouse septic system at Rice Creek Chain of Lakes Regional Park (2nd of 6 projects in this grant)
Rice Creek Chain of Lakes Park Reserve, reconstruct Chamonix golf course clubhouse septic system. (2 of 6 projects financed with grant.)
Rice Creek Chain-of-Lakes Park Reserve
Sec. 4. METROPOLITAN COUNCIL$15,763,000$16,141,000
(a) $15,763,000 the first year and $16,141,000 the second year are to be distributed under Minnesota Statutes, section 85.53, subdivision 3. The Metropolitan Council may use a portion of this appropriation to provide grants for metropolitan parks and trails of regional or statewide significance within the metropolitan area that are not eligible under Minnesota Statutes, section 85.53, subdivision 3.
(b) The Metropolitan Council shall submit a report on the expenditure and use of money appropriated under this section to the legislature as provided in Minnesota Statutes, section 3.195, by March 1 of each year. The report must detail the outcomes in terms of additional use of parks and trails resources, user satisfaction surveys, and other appropriate outcomes.
Increased visits to park over time.
At Rice Creek Chain of Lakes Park Reserve design and engineering is underway and construction of the Chomonix Golf Course Clubhouse Septic System is substantially complete. Final completion is expected by June 2014. Visits to park increased by about 36,000 between 2012 and 2014.