Mississippi River - Headwaters Watershed Restoration and Protection Strategy (WRAPS) - Phase 2

Project Details by Fiscal Year
2017 Fiscal Year Funding Amount
$48,350
Fund Source
Clean Water Fund
Recipient
Hubbard County SWCD
Recipient Type
Local/Regional Government
Status
In Progress
Start Date
January 2015
End Date
December 2017
Activity Type
Education/Outreach/Engagement
Planning
Restoration/Enhancement
Counties Affected
Becker
Beltrami
Cass
Clearwater
Hubbard
Itasca
2017 Fiscal Year Funding Amount
$48,350
Number of full time equivalents funded
0.61
Project Overview

Several important milestones will be completed during this phase of the Mississippi River (Headwaters) Watershed Restoration and Protection Strategy (WRAPS) project. These milestones will include the completion of the Stressor ID & Watershed Monitoring and Assessment Reports, the completion of the Zonation Modeling watershed priority planning process (through the continuation of the Civic Engagement project component), and the development of the overall WRAPS report. Currently, this watershed has few listed conventional impairments; however, it is possible that additional impairments may have been identified during the Intensive Watershed Monitoring and subsequent watershed assessment process. This project will significantly contribute to establishing the foundation for long-term public participation in surface water protection and restoration activities throughout the watershed.

Project Details

Mississippi River - Headwaters Watershed

Project Manager
First Name
Julie
Last Name
Kingsley
Organization Name
Hubbard County SWCD
Street Address
212 1/2 2nd St
City
W Park Rapids
State
MN
Zip Code
56470
Phone
(218) 732-0121