Local match for federal grant to construct 1.1 miles of North Urban Regional Trail

Project Details by Fiscal Year
2011 Fiscal Year Funding Amount
$96,000
Fund Source
Parks & Trails Fund
Recipient
Dakota County
Status
Completed
Start Date
July 2010
End Date
June 2013
Counties Affected
Dakota
Dakota
Project Overview

North Urban Regional Trail, complete local match to $794,300 federal transportation grant to construct 1.1 miles of North Urban Regional Trail.

Project Details

Lebanon Hills Regional Park

Legal Citation / Subdivision
M.L. 2009, Chp. 172, Art. 3, Sec. 3 (a) (SFY 2011) PTLF
Appropriation Language

Sec. 3. METROPOLITAN COUNCIL$12,641,000$15,140,000
(a) $12,641,000 the first year and $15,140,000 the second year are from the parks and trails fund to be distributed as required under new Minnesota Statutes, section 85.535, subdivision 3, except that of this amount, $40,000 the first year is for a grant to Hennepin County to plant trees along the Victory Memorial Parkway.
(b) The Metropolitan Council shall submit a report on the expenditure and use of money appropriated under this section to the legislature as provided in Minnesota Statutes, section 3.195, by March 1 of each year. The report must detail the outcomes in terms of additional use of parks and trails resources, user satisfaction surveys, and other appropriate outcomes.
(c) Grant agreements entered into by the Metropolitan Council and recipients of money appropriated under this section shall ensure that the funds are used to supplement and not substitute for traditional sources of funding.
(d) The implementing agencies receiving appropriations under this section shall give consideration to contracting with the Minnesota Conservation Corps for contract restoration, maintenance, and other activities.

2011 Fiscal Year Funding Amount
$96,000
Other Funds Leveraged
$794,300
Proposed Measurable Outcome(s)

Growth in trail visits over time. The 2014 annual report will compare trail visit growth from 2011 (pre-construction) to 2013 (post-construction) to measure the effect of constructing this trail.

Measurable Outcome(s)

The Dakota County Board of Commissioners selected preferred alignment. Construction documents are being prepared. Land acquisition on-track for completion by March 31, 2014. Project is on-schedule and construction started in 2014 and scheduled to be complete in 2015.

Source of Additional Funds

Federal

Recipient Board Members
County Board
Project Manager
First Name
Steve Sullivan
Street Address
14955 Galaxie Ave
City
Apple Valley
State
MN
Zip Code
55124
Phone
952-891-7088
Email
steve.sullivan@co.dakota.mn.us
Administered By
Administered by
Location

390 N. Robert Street
St. Paul, MN 55101

Phone
651-602-1000