Hyland Lake Park Reserve Nature Center Improvements

Project Details by Fiscal Year
2022 Fiscal Year Funding Amount
$650,000
Fund Source
Parks & Trails Fund
Recipient
Three Rivers Park District
Status
In Progress
Start Date
July 2021
End Date
June 2025
Project Overview

Multiple projects within west side of Hyland Park Reserve:
-Engineering and construction of 40 additional parking stalls at Richardson Nature Center
-Engineering and construction of parking lot lighting upgrades at Richardson Nature Center
-Engineering and reconstruction of 0.1 miles of paved trails at Richardson Nature Center
-Engineering and construction for mill and overlay of 2.3 acres of pavement at Richardson Nature Center and the nearby Operations Center

Project Details

Hyland Lake Park Reserve

Legal Citation / Subdivision
M.L. 2021, 1st Special, Chp. 1, Art. 3, Sec. 4 (SFY 2022) PTLF
Appropriation Language

Sec. 4. METROPOLITAN COUNCIL$21,712,000$22,149,000
(a) $12,641,000 the first year and $15,140,000 the second year are from the parks and trails fund to be distributed as required under new Minnesota Statutes, section 85.535, subdivision 3, except that of this amount, $40,000 the first year is for a grant to Hennepin County to plant trees along the Victory Memorial Parkway.
(b) The Metropolitan Council shall submit a report on the expenditure and use of money appropriated under this section to the legislature as provided in Minnesota Statutes, section 3.195, by March 1 of each year. The report must detail the outcomes in terms of additional use of parks and trails resources, user satisfaction surveys, and other appropriate outcomes.
(c) Grant agreements entered into by the Metropolitan Council and recipients of money appropriated under this section shall ensure that the funds are used to supplement and not substitute for traditional sources of funding.
(d) The implementing agencies receiving appropriations under this section shall give consideration to contracting with the Minnesota Conservation Corps for contract restoration, maintenance, and other activities.

2022 Fiscal Year Funding Amount
$650,000
Proposed Measurable Outcome(s)

Addition of 40 parking stalls at Richardson Nature Center
-Upgrade of Richardson parking lot lighting
-Reconstruction of 0.1 miles of paved trails at Richardson Nature Center
-Engineering and construction for mill and overlay of 2.3 acres of pavement at Richardson and at the Operations Center

Measurable Outcome(s)

Addition of 40 parking stalls at Richardson Nature Center
Upgrade of Richardson Nature Center parking lot lighting
Reconstruction of 0.1 miles of paved trails at Richardson Nature Center
Engineering and construction for mill and overlay of 2.3 acres of pavement at Richardson and the Operations Center

Recipient Board Members
City Council
Project Manager
First Name
Boe Carlson
Street Address
25 W 4th St #400
City
Saint Paul
Phone
763-559-9000
Email
bcarlson@threeriversparkdistrict.org
Administered By
Administered by
Location

390 N. Robert Street
St. Paul, MN 55101

Phone
651-602-1000