Design, engineer & build pole shed, electrical work at St. Croix Bluffs Regional Park (year 1 of 2)

Project Details by Fiscal Year
2019 Fiscal Year Funding Amount
$604,953
2018 Fiscal Year Funding Amount
$705,097
Fund Source
Parks & Trails Fund
Recipient
Washington County
Status
Completed
Start Date
July 2017
End Date
June 2020
Counties Affected
Washington
Washington
Project Overview

Design, engineer & build pole shed, electrical work at St. Croix Bluffs Regional Park (year 1 of 2)

Project Details

St. Croix River Bluffs Regional Park

Legal Citation / Subdivision
M.L. 2017, Chp. 91, Art. 3, Sec. 4 (SFY 2019) PTLF
Appropriation Language

Sec. 4. METROPOLITAN COUNCIL$16,584,000$18,891,000
(a) $16,584,000 the first year and $18,891,000 the second year are for distribution according to Minnesota Statutes, section 85.53, subdivision 3.
(b) Money appropriated under this section and distributed to implementing agencies must be used only to fund the list of projects approved by the elected representatives of each of the metropolitan parks implementing agencies. Projects funded by the money appropriated under this section must be substantially consistent with the project descriptions and dollar amounts approved by each elected body. Any funds remaining after completion of the listed projects may be spent by the implementing agencies on projects to support parks and trails.
(c) Grant agreements entered into by the Metropolitan Council and recipients of money appropriated under this section must ensure that the funds are used to supplement and not substitute for traditional sources of funding.
(d) The implementing agencies receiving appropriations under this section shall give consideration to contracting with Conservation Corps Minnesota for restoration, maintenance, and other activities.

2019 Fiscal Year Funding Amount
$604,953
Proposed Measurable Outcome(s)

Measure and report the number and types of improvements or expansions made to building, and the change in number of reservations.

Measurable Outcome(s)

Improvements made to the new pole barn include new heated floor, new racking system for storage, 18 vehicle parking spots, new fresh air exchanger, three garage doors, new access road to building, two holding tanks for wastewater, a new transformer
Number of paid nights stayed for St. Croix Bluffs Regional Park campgrounds were 4,824 from 4/27/2018-10/21/2018, 5,130 from 4/26/2109-10/20/2019, and 5,033 from 6/1/2020-10/18/2020 (partial season due to COVID)

Recipient Board Members
City Council
Legal Citation / Subdivision
M.L. 2017, Chp. 91, Art. 3, Sec. 4 (SFY 2018) PTLF
Appropriation Language

Sec. 4. METROPOLITAN COUNCIL$16,584,000$18,891,000
(a) $16,584,000 the first year and $18,891,000 the second year are for distribution according to Minnesota Statutes, section 85.53, subdivision 3.
(b) Money appropriated under this section and distributed to implementing agencies must be used only to fund the list of projects approved by the elected representatives of each of the metropolitan parks implementing agencies. Projects funded by the money appropriated under this section must be substantially consistent with the project descriptions and dollar amounts approved by each elected body. Any funds remaining after completion of the listed projects may be spent by the implementing agencies on projects to support parks and trails.
(c) Grant agreements entered into by the Metropolitan Council and recipients of money appropriated under this section must ensure that the funds are used to supplement and not substitute for traditional sources of funding.
(d) The implementing agencies receiving appropriations under this section shall give consideration to contracting with Conservation Corps Minnesota for restoration, maintenance, and other activities.

2018 Fiscal Year Funding Amount
$705,097
Proposed Measurable Outcome(s)

Measure and report the number and types of improvements or expansions made to building, and the change in number of reservations.

Measurable Outcome(s)

Improvements made to the new pole barn include new heated floor, new racking system for storage, 18 vehicle parking spots, new fresh air exchanger, three garage doors, new access road to building, two holding tanks for wastewater, a new transformer
Number of paid nights stayed for St. Croix Bluffs Regional Park campgrounds were 4,824 from 4/27/2018-10/21/2018, 5,130 from 4/26/2109-10/20/2019, and 5,033 from 6/1/2020-10/18/2020 (partial season due to COVID)

Recipient Board Members
City Council
Project Manager
First Name
Sandy Breuer
Street Address
14949 62nd St N
City
Stillwater
State
MN
Zip Code
55082
Phone
651-430-4303
Email
sandy.breuer@co.washington.mn.us
Administered By
Administered by
Location

390 N. Robert Street
St. Paul, MN 55101

Phone
651-602-1000