Design, engineer & build pedestrian circulation & parking at Phalen-Keller Regional Park (reallocation)

Project Details by Fiscal Year
2016 Fiscal Year Funding Amount
$11
Fund Source
Parks & Trails Fund
Recipient
St. Paul Parks & Recreation
Status
Completed
Start Date
July 2015
End Date
June 2018
Project Overview

Design, engineering and construction of pedestrian and vehicular circulation and parking. Includes grading, stormwater management and erosion control.

Project Details

Phalen-Keller Regional Park/St Paul

Legal Citation / Subdivision
M.L. 2015, Chp. 2, Art. 3, Sec. 4 (SFY 2016) PTLF
Appropriation Language

Sec. 4. METROPOLITAN COUNCIL$17,237,000$18,067,000
(a) $17,237,000 the first year and $18,067,000 the second year are for distribution according to Minnesota Statutes, section 85.53, subdivision 3.
(b) Money appropriated under this section and distributed to implementing agencies must be used to fund the list of recommended projects in the report submitted pursuant to Laws 2013, chapter 137, article 3, section 4, paragraph (o). Projects funded by the money appropriated under this section must be substantially consistent with the project descriptions and dollar amounts in the report. Any funds remaining after completion of the listed projects may be spent by the implementing agencies on projects to support parks and trails.
(c) Grant agreements entered into by the Metropolitan Council and recipients of money appropriated under this section must ensure that the funds are used to supplement and not substitute for traditional sources of funding.
(d) The implementing agencies receiving appropriations under this section shall give consideration to contracting with Conservation Corps Minnesota for restoration, maintenance, and other activities.

2016 Fiscal Year Funding Amount
$11
Proposed Measurable Outcome(s)

Measure and report the square feet of parking lot restored, the linear feet of trail restored and the linear feet of road restored within park.

Measurable Outcome(s)

1. 129,020 sq. ft. park lot restored
2. 1,500 linear ft. pedestrian trail restored, 800 linear ft. bike trail restored
3. 440 linear ft. road restored

Recipient Board Members
City Council
Project Manager
Street Address
25 W 4th St #400
City
Saint Paul
Phone
651-266-6409
Email
michale.hahm@ci.stpaul.mn.us
Administered By
Administered by
Location

390 N. Robert Street
St. Paul, MN 55101

Phone
651-602-1000