2016 Lake Emily Watershed BMP Targeted Implementation Project

Project Details by Fiscal Year
2016 Fiscal Year Funding Amount
$287,500
Fund Source
Clean Water Fund
Recipient
Pope SWCD
Recipient Type
Local/Regional Government
Status
Completed
Start Date
January 2016
End Date
February 2020
Activity Type
Grants/Contracts
Counties Affected
Pope
Pope
Project Overview

The Lake Emily Watershed BMP Targeted Implementation Project will provide funding for 48 water and sediment control projects and potential shoreline and riparian restoration. This work would address surface water quality sources identified in the water plan (Section 2-pg 11) including direct drainage from the Lake Emily sub-watersheds (070200050304, 070200050303, 070200050203, 070200050201, 070200050202) the Little Chippewa, and from upstream discharge between Lake Emily and Lake Minnewaska. The Pope County Water Plan has identified surface water quality and erosion control as the top two priority resource concerns in the 2013-2023 Comprehensive Water Plan (page 1-17). These two priorities account for 33% of the phosphorus loading to Lake Emily. Lake Emily is identified in the Eight Lake TMDL study and the Pope County Water plan as being impaired for excessive nutrients. In recent years, Pope County has had rainfall events 2-4 times a summer that have caused severe gully erosions. By utilizing water and sediment control basins as identified in the TMDL implementation plan (section 1.1 page 3) and the Pope County Water Plan (2-25) as a method of lowering the annual load of TSS and TP water quality trends improve and not decline. This proposal will target the highest contributing direct drainage areas to implement projects. Based on averages calculated from past WASCOBs in the West Central area these projects have the potential to reduce the sediment load leaving the field by 1,121 Tons/year of TSS and 960 lbs/year of TP which will directly address 15% of Lake Emily's TP reduction goal for direct drainage from storm water runoff. A Water Quality Decision Support App (WQDSA) has also been completed and projects identified in this application in the medium to highest category will receive priority for funding.

Competitive Grant Making Body
Board Members and Qualifications

See http://www.bwsr.state.mn.us/aboutbwsr/index.html and http://www.bwsr.state.mn.us/aboutbwsr/boarddirectory.pdf

Advisory Group Members and Qualifications

See http://www.bwsr.state.mn.us/aboutbwsr/index.html

Conflict of Interest Contact

Marcey Westrick

Legal Citation / Subdivision
Laws of MN 2015 1st Special Session Chapter 2, Article 2, Section 7
Appropriation Language

Projects and Practices 2016: Laws of MN 2015 First Special Session Chapter 2, Article 7, Section 7

2016 Fiscal Year Funding Amount
$287,500
Other Funds Leveraged
$71,875
Direct expenses
$287,500
Administration costs
$2
Number of full time equivalents funded
0.18
Proposed Measurable Outcome(s)

Based on averages calculated from recently constructed WASCOBs in the West Central Area II these WASCOBs have the potential to reduce sediment load by 1,121 T/yr, and 960 lbs/yr of total phosphorus. This project will also result in meeting a total reduction of 15% of the 35% TMDL goal needed to delist Lake Emily completely.

Measurable Outcome(s)

This project resulted in an estimated annual reduction of 1131.02 lbs of phosphorus, 976.53 tons of sediment, and 2938.06 tons per year of soil loss.

Proposed Outcomes Achieved
achieved proposed outcomes
Source of Additional Funds

LOCAL LEVERAGED FUNDS

Project Manager
First Name
Holly
Last Name
Kovarik
Organization Name
Pope SWCD
Street Address
1680 N. Franklin Street
City
Glenwood
State
MN
Zip Code
56334
Phone
320-634-4278
Email
holly.kovarik@mn.nacdnet.net
Administered By
Administered by
Location

520 Lafayette Road North
St. Paul, MN 55155

Phone
651- 296-3767