Mud Lake Subwatershed Assessment

Project Details by Fiscal Year
2015 Fiscal Year Funding Amount
$39,968
Fund Source
Clean Water Fund
Recipient
Minnehaha Creek WD
Recipient Type
Local/Regional Government
Status
Completed
Start Date
March 2015
End Date
December 2018
Activity Type
Grants/Contracts
Counties Affected
Hennepin
Hennepin
Project Overview

This project will develop a plan that identifies several stormwater best management practices (BMPs) for the City of St. Bonifacius and surrounding rural areas. Implementation of these BMPs will improve water quality in Mud Lake and Halsted's Bay. A watershed model (EPA-SWMM and P8) will be developed to determine existing phosphorus and sediment loading from the City of Bonifacius and adjacent rural areas draining to Mud Lake. Model output will be used to identify several potential locations for stormwater BMPs throughout the city and surrounding areas. Preliminary designs for each practice will be developed to determine size, cost, and feasibility. A final planning level report will be produced that summarizes the methods and results of the modeling analysis and recommended rural and city stormwater BMPs.

Competitive Grant Making Body
Advisory Group Members and Qualifications
Conflict of Interest Disclosed
No
Conflict of Interest Contact

Nicole Clapp

Legal Citation / Subdivision
Laws of Minnesota 2013, Regular Session chapter 137
2015 Fiscal Year Funding Amount
$39,968
Other Funds Leveraged
$23,750
Direct expenses
$95,000
Proposed Measurable Outcome(s)

This project will result in an inventory and inspection of four drainage ditches in Blue Earth County.

Measurable Outcome(s)

A subwatershed retrofit assessment for the City of St. Bonifacius and surrounding rural areas was completed. A list of approximately 40 BMPs were identified and incorporated into the report. BMPs include retrofitting existing stormwater ponds, wetland restorations, agricultural BMPs, and the use on in-line alum treatment.
The model was successfully developed and updated to inform our understanding of watershed phosphorus loading.
The study generated a list of approximately 40 total BMPs (before cost-benefit prioritization). After cost-benefit analysis, this list was reduced to approximately 20 high return on investment priority projects. Both lists are incorporated into the final report.
A final report has been assembled that identified approximately 20 BMPs that are priorities for implementation based on their cost benefit analysis (cost/lbs p removed). This report has been circulated to our City partners and will facilitate implementation of stormwater BMPs in the Mud Lake subwatershed.

Proposed Outcomes Achieved
Achieved proposed outcomes
Source of Additional Funds

LOCAL LEVERAGED FUNDS

Recipient Board Members
Board information for grantees can be found within contact directories on BWSR's website under Operational Resources, "About Our Partners".
Project Manager
First Name
Anna
Last Name
Brown
Organization Name
Minnehaha Creek WD
Street Address
15320 Minnetonka Blvd
City
Minnetonka
State
MN
Zip Code
55345
Phone
952-641-4522 x 522
Email
abrown@minnehahacreek.org
Administered By
Administered by
Location

520 Lafayette Road North
St. Paul, MN 55155

Phone
651- 296-3767