Pine River Watershed WBIF Phase 3
The Pine River Watershed Policy Committee is ready to apply for its third phase of Watershed-based Implementation Funding. The phase 1 allocation has been completely spent and reconciled with BWSR. The Pine River Watershed Phase 2 allocation has spent/encumbered $312,214.84 out of $482,000. The remaining $169,785.06 is mostly remaining in project development, technical assistance, and grant administration. Furthermore, some categories within the last work plan have been completely spent and continue to have landowners ready but on a waiting list. For example, 11 landowners are waiting to install shoreline restoration projects on priority lakes within the watershed. At this time, the LGU's are ready to apply for the next phase of funding.
Annie Felix-Gerth
(a) $39,500,000 the first year and $39,500,000 the second year are for grants to implement state-approved watershed-based plans. The grants may be used to implement projects or programs that protect, enhance, and restore surface PreviouswaterNext quality in lakes, rivers, and streams; protect groundwater from degradation; and protect drinking PreviouswaterNext sources. Projects must be identified in a comprehensive watershed plan developed under the One Watershed, One Plan program and seven-county metropolitan groundwater or surface PreviouswaterNext management frameworks as provided for in Minnesota Statutes, chapters 103B, 103C, 103D, and 114D. Grant recipients must identify a nonstate match and may use other legacy funds to supplement projects funded under this paragraph. This appropriation may be used for: (1) implementing state-approved plans, including within the following watershed planning areas (see Chapter 40 Article 2 Section 6(a) (2) for the list of watershed planning areas: seven-county metropolitan groundwater or surface PreviouswaterNext management frameworks; and(3) other comprehensive watershed management plan planning areas that have a board-approved and local-government-adopted plan as authorized in Minnesota Statutes, section 103B.801. The board must establish eligibility criteria and determine whether a planning area is ready to proceed and has the nonstate match committed.
-Write 25 forest stewardship plans for 2,500 acres.
-retain 2.76 pounds of phos. and .77 tons of sediment from the Crosslake project
-stabilize 250 linear ft of the Pine River
-host 6 smart salting trainings
-Implement shoreline restoration projects
LOCAL LEVERAGED FUNDS