2022 Red Lake County Multipurpose Drainage Management Grant
Red Lake County SWCD will continue to work cooperatively with the Red Lake County Ditch Authority, and the landowners involved to reduce erosion and sedimentation, reduce peak flows and flooding, improve water quality, and protect drainage system efficiency for priority Chapter 103E drainage systems by installing an estimated twenty-three multipurpose drainage management practices. The data identified which county ditch systems, were contributing to these impairments (TSS, E.coli, and DO), in the Clearwater River. The priority Chapter 103E drainage system is County Ditch 57, including the contributing ditch branches. These proposed Ag Practices are the strategies that will assist in achieving the sediment reduction goals. The estimated twenty-three priority County Ditch 57 locations were targeted from the information gathered from the 2014 & 2015 Drainage Ditch Inventory and Inspection grant. The estimated annual reduction in sediment being delivered to Clearwater River is 397 tons per year for the entire project.
Red Lake County SWCD advanced the Drainage Ditch Inventory process by using the Water Quality Decision Support System (WQDSS) tool, created by the International Waters Institute, to help prioritize areas where Multipurpose Drainage Management practices are needed. The Stream Power Index layer of the WQDSS tool indicates which flow paths have the highest erosive power and greatest potential for erosion. This tool helped assist the District with prioritizing and targeting these Multipurpose Drainage Management practice locations.
Red Lake County SWCD has already been proactive in selecting locations where multipurpose drainage management practices are needed to reduce soil loss, eliminate sediment deposition in the impaired ditch systems, improve water quality, and reduce maintenance costs with the installation of 160 NRCS Conservation Practice Code 410 practices over the past ten years.
Annie Felix-Gerth
(j) $850,000 the first year and $850,000 the second year are for technical assistance and grants for the conservation drainage program, in consultation with the Drainage Work Group, coordinated under Minnesota Statutes, section 103B.101, subdivision 13, and including projects to improve multipurpose water management under Minnesota Statutes, section 103E.015.
The 23 practices will reduce sediment loading by 396.64 ton/year, soil loss by 779.41 tons/year, and phosphorus by 284.69 pounds/year. The average cost effectiveness is $204.88/ton/year of sediment and $285.44/pound/year of phosphorus.
Grant funds funded a total of 44 side water inlet practices were installed along the CD57 system resulting in a load reduction of 296 tons/year of sediment, 31 pounds/year of phosphorus, and 594 pounds/year of nitrogen. The final pollution reduction estimates were lower than the estimates in the grant application despite completing more projects than planned because the Red Lake SWCD has transitioned to using the PTMApp tool, which they feel provides a more realistic estimate of project benefits.
LOCAL LEVERAGED FUNDS