Minnesota's Legacy

All Projects

Showing 1 - 40 of 120 | Export projects
Recipient
Chisago SWCD
2015 Fiscal Year Funding Amount
$150,000
Fund Source

Two large, actively eroding gullies located a few miles apart in Amador Township are contributing tremendous loads of phosphorus and sediment to the St. Croix River. One gully (Gully A) includes a major agricultural gully, severe road erosion, and sediment deposits of a foot or more thick in a state park. The second gully (Gully B) is over 4 feet deep, adjacent to a road, and is an annual problem. Stabilizing these two gullies will greatly reduce the sediment and phosphorus loading to the St. Croix River, which will help meet the reduction goal of the Lake St.

Chisago
Recipient
Chisago SWCD
2015 Fiscal Year Funding Amount
$30,000
Fund Source

Using a previous escarpment gully project as a model, the Chisago Soil and Water Conservation District will complete a similar inventory of actively eroding gullies along the Lower Sunrise River from the Kost Dam south to the confluence with the St. Croix, which includes the North Branch of the Sunrise, Hay Creek, and the Sunrise River main branch. There are major erosion issues along this stretch of river, no organized and efficient way to begin work in the area. The inventory report will provide the missing link.

Chisago
Recipient
Chisago SWCD
2015 Fiscal Year Funding Amount
$30,000
Fund Source

The Chisago Soil and Water Conservation District has been successful in implementing Best Management Practices in certain targeted locations within the county, including the prioritized and assessed areas of Chisago City, Lindstrom, and Center City. However, there are many areas that want to implement conservation projects but aren't within targeted areas. This award will empower community partners, especially lake associations, to award grants for rain gardens, shoreline buffers, and other worthwhile projects to improve water quality.

Chisago
Recipient
Chisago SWCD
2016 Fiscal Year Funding Amount
$220,500
Fund Source

The Chisago Soil and Water Conservation District (SWCD) has had such great success implementing gully stabilization projects along the St. Croix River escarpment that all of the current grant funding has been encumbered towards projects. Two large gully projects, one in the City of Taylors Falls and a second nearby in Interstate State Park, are lined up and ready to go as soon as funding is secured. Both of these gullies are large and have been actively eroding for many years, depositing large loads of sediment and phosphorus directly into the St. Croix River.

Chisago
Recipient
Ramsey Conservation District
2017 Fiscal Year Funding Amount
$150,000
Fund Source

The purpose of this program is to engage community groups for the installation of community accessible rain gardens and other water quality best management practices in Ramsey County. The goal is to install 6-12 storm water best management projects that will help protect and improve water quality of surrounding lakes. The installed practices will reduce an estimated 10 acre-feet of storm water runoff, 9 pounds of phosphorous, and 3 tons of sediment annually. Significant measurable outputs, with development of long-term partnerships, are primary objectives for this program.

Ramsey
Recipient
Chisago SWCD
2017 Fiscal Year Funding Amount
$250,000
Fund Source

Goose, East and West Rush Lakes are not meeting state water quality standards due to excessive phosphorus. These are three of the worst lakes in Chisago County in terms of water quality, yet also some of the most heavily used lakes for recreation. The quality of the water in the St. Croix River is directly influenced by the poor quality water leaving East Rush, West Rush, and Goose Lakes.

Chisago
Recipient
Stearns SWCD
2017 Fiscal Year Funding Amount
$392,500
Fund Source

This project will address nutrient impairments of the Sauk River and Sauk River Chain of Lakes (SRCL) by minimizing runoff from 5 high priority feedlots. Specifically, contaminated runoff from 5 feedlots upstream of the SRCL will be eliminated. The sites were prioritized based on the Minnesota Feedlot Annualized Runoff Model index ratings and the location of these feedlots are within a Drinking Water Supply Management Areas.

Stearns
Recipient
Stearns SWCD
2015 Fiscal Year Funding Amount
$210,000
Fund Source

The Stearns County Soil and Water Conservation District will hire an Accelerated Water Quality Technician to focus on projects in the Middle Sauk area showing the greatest pollution reductions. After identifying and prioritizing targeted sites with the highest pollution potential, the Stearns County SWCD will begin surveys and designs and complete them in a timely fashion while current implementation funds are available. The accelerated survey and design in Stearns County will relieve our natural resources of the current strain put on them by the environment and land use.

Stearns
Recipient
Farmers, Rural Landowners, and Agricultural Supply Businesses
2019 Fiscal Year Funding Amount
$75,000
2018 Fiscal Year Funding Amount
$75,000
2017 Fiscal Year Funding Amount
$75,000
2016 Fiscal Year Funding Amount
$75,000
2015 Fiscal Year Funding Amount
$200,000
2014 Fiscal Year Funding Amount
$200,000
2013 Fiscal Year Funding Amount
$4,500,000
2012 Fiscal Year Funding Amount
$4,500,000
2011 Fiscal Year Funding Amount
$2,500,000
2010 Fiscal Year Funding Amount
$2,000,000
Fund Source

The AgBMP Loan Program provides needed funding for local implementation of clean water practices at an extremely low cost, is unique in its structure and is not duplicated by any other source of funding.The AgBMP loan program provides 3% loans through local lenders to farmers, rural landowners, and agriculture supply businesses.

Anoka
Becker
Blue Earth
Brown
Carver
Cook
Cottonwood
Dakota
Dodge
Douglas
Faribault
Fillmore
Freeborn
Goodhue
Grant
Houston
Hubbard
Jackson
Kandiyohi
Lac qui Parle
Le Sueur
Lincoln
Lyon
Martin
Morrison
Mower
Murray
Nicollet
Olmsted
Pipestone
Pope
Redwood
Renville
Rice
Rock
Scott
Sherburne
Sibley
St. Louis
Stearns
Steele
Stevens
Todd
Traverse
Wabasha
Waseca
Washington
Watonwan
Winona
Yellow Medicine
Recipient
Peer Engineering
2014 Fiscal Year Funding Amount
$115,910
Fund Source

Peer Engineering, Inc. (Peer) will evaluate and recommend to MPCA groundwater monitoring staff prospective sites/locations for the installation of groundwater monitoring wells to evaluate contaminant/pollutant concentrations from various sources. Peer will oversee the installation of monitoring wells by retaining a state drilling contractor or preparing bid documents to retain well driller through the Department of Administration. Superfund staff will assist in the project by providing oversight of contractual requirements and provide technical assistance as needed.

Dakota
Hennepin
Mower
Rice
Washington
Recipient
Metropolitan Council-Environmental Services
2013 Fiscal Year Funding Amount
$405,500
Fund Source

This project will provide condition monitoring and problem investigation monitoring at the following sites.
Mississippi River: Tributaries include Bassett Creek, Cannon River, Crow River, and Minnehaha Creek.
Minnesota River: Tributaries include Eagle Creek,Riley Creek, and Valley Creek tributary to the St. Croix River

Anoka
Benton
Carver
Chisago
Dakota
Hennepin
Isanti
Le Sueur
McLeod
Meeker
Mille Lacs
Morrison
Nicollet
Pine
Ramsey
Renville
Rice
Scott
Sherburne
Sibley
Stearns
Washington
Wright
Recipient
Sauk River WD
2015 Fiscal Year Funding Amount
$80,715
Fund Source

The Ashley Creek and Adley Creek Inventory Project will involve desk top analysis and a field scale inventory of riparian areas to determine priority areas to install erosion control Best Management Practices and vegetative buffers for nutrient reduction. Assessments will also be made for potential E.coli bacteria sources. Inventory data will be shared with local partners to further develop an implementation plan to address nutrient loading and the listed impairments on each creek.

Stearns
Recipient
Comfort Lake-Forest Lake WD
2014 Fiscal Year Funding Amount
$360,750
Fund Source

This project will focus, on a sub-regional scale, on water quality improvements targeted at concentrated runoff flows generated from upstream, developed portions of the City of Forest Lake. This project will work to modify an existing wetland complex located in publicly owned Bixby Park of Forest Lake to increase water quality treatment potential and storage capacity. The project will also incorporate an innovative iron-enhanced sand filter which will remove dissolved phosphorus, resulting in a 206 pound/year reduction of phosphorous and a 27 tons/year removal of sediment.

Washington
Recipient
Washington Conservation District
2016 Fiscal Year Funding Amount
$160,000
Fund Source

In recent years, nutrient enrichment has occurred in Lake St. Croix due to increasing amounts of phosphorus entering the lake from the watershed. According to the TMDL, approximately half of the phosphorus-loading to Lake St. Croix is in the soluble form, and agriculture has been identified as one of the largest contributors of that phosphorus. In addition to the TMDL, subwatershed analyses were completed to identify, assess, and prioritize phosphorus-reducing practices in rural areas draining to Lake St. Croix in Washington County. This project will reduce phosphorus discharges to the St.

Washington
Recipient
Comfort Lake-Forest Lake WD
2017 Fiscal Year Funding Amount
$88,000
Fund Source

Bone Lake and upstream Moody Lake are the headwaters of the Comfort Lake-Forest Lake Watershed District northern flow network, and as such, their water quality sets the stage for downstream waters, particularly Comfort Lake, the Sunrise River, and ultimately Lake St. Croix. This project proposes the implementation of six wetland restorations located along the tributary identified as the single highest source of phosphorus loading to Bone Lake. These wetland restorations are estimated to reduce watershed phosphorus loads to Bone Lake by 50 pounds per year.

Chisago
Washington
Recipient
Browns Creek WD
2014 Fiscal Year Funding Amount
$33,500
Fund Source

Brown's Creek is one of the few remaining cold water fisheries in the Metropolitan Area; however, it is impaired due to high suspended solids and high water temperatures. To understand the extensive and complex in-stream temperature and local climate data already collected by the Brown's Creek Watershed District, this grant will facilitate the development of a thermal model to determine thermal sources and cost-effective management projects and practices to reduce thermal loading to Brown's Creek.

Washington
Recipient
Browns Creek WD
2015 Fiscal Year Funding Amount
$204,350
Fund Source

The Watershed District is partnering with the City of Stillwater to reduce sediment and thermal loading to Brown's Creek from existing impervious gravel parking lot and paved roads to achieve Total Maximum Daily Load water quality goals in this reach of Brown's Creek.

Washington
Recipient
Browns Creek WD
2017 Fiscal Year Funding Amount
$51,525
Fund Source

The purpose of the project is to target the type and location of riparian vegetation restoration needed to shade three miles of unforested buffer on Brown's Creek, a metro area trout stream impaired for thermal and sediment loading. The project will conduct a riparian shading analysis, cost-benefit analysis, and modeling of restoration scenarios based on field measurements of shade in the unforested buffer of Brown's Creek.

Washington
Recipient
Area 4 - Metropolitan SWCDs Technical Service Area
2016 Fiscal Year Funding Amount
$200,000
Fund Source

Once thought to have an essentially inexhaustible groundwater supply, Minnesotans are now realizing our rates of use are regionally unsustainable. Recent advanced modeling by the MN DNR and Metropolitan Council of aquifer supplies, in conjunction with predicted demand, indicate the major metropolitan area aquifers are currently subject to extraction rates that exceed recharge. Simply stated, we are mining our groundwater.

Scott
Recipient
Carnelian-Marine-St. Croix WD
2015 Fiscal Year Funding Amount
$108,431
Fund Source

This project will implement watershed load reduction practices to restore the top priority water body in the Carnelian Marine St. Croix Watershed District in northeast Washington County. Recently completed prioritization and targeting efforts have identified several Best Management Practice opportunities around goose Lake, the number one priority for implementation practices.

Washington
Recipient
Washington Conservation District
2012 Fiscal Year Funding Amount
$14,142
Fund Source

This project addresses the identified need for an Implementation Plan that provides an overall roadmap for the effort it will take to meet the Carnelian Marine St. Croix Multi-Lakes Total Maximum Daily Load (TMDL). An Implementation Plan will be developed, with involvement of the Project Partners and stakeholder groups, that sets forth prioritized strategies for attaining the TMDL and a method for tracking the progress of those efforts. The Implementation Plan will be restoration-focused, but will include protection-oriented information/actions as well.

Anoka
Chisago
Isanti
Pine
Ramsey
Washington
Recipient
Washington Conservation District
2010 Fiscal Year Funding Amount
$103,598
Fund Source

Continued TMDL project to support next phases associated with completion of TMDL's for ten lakes in the Carnelian Marine Saint Croix Watershed District (CMSCWD). Ten lakes are; East Boot, Fish, Goose, Hay, Jellum’s, Long, Loon, Louise, Mud and South Twin.

Anoka
Chisago
Isanti
Pine
Washington
Recipient
Chisago SWCD
2014 Fiscal Year Funding Amount
$250,000
Fund Source

In 2010, Legislation allocated Clean Water Fund (CWF) dollars to the Anoka Conservation District to initiate an 11 county metro subwatershed assessment program. The purpose of subwatershed assessments is to improve water quality, increase groundwater recharge and reduce runoff volumes. These goals are achieved by identifying opportunities in the subwatersheds most contributing to the degradation of the high priority water bodies and developing designs for Best Management Practices (BMPs) that treat stormwater runoff.

Chisago
Recipient
Sauk River WD
2016 Fiscal Year Funding Amount
$95,500
Fund Source

The Chain of Lakes Targeted Reduction project will utilize Clean Water Funds to address bank erosion and install vegetated buffers along tributaries to the Eden Valley Chain of Lakes using the SRWD's incentivized Hayed Buffer Program. The Eden Valley Chain of Lakes (Vails Lake, Eden Lake and North Browns Lake) drain into the main segment of the Sauk River Chain of Lakes (SRCL) from the south. Impaired for excessive nutrients, this southern series of lakes is influenced by inflows from private ditches and perennial and intermittent streams.

Stearns
Recipient
Stearns SWCD
2015 Fiscal Year Funding Amount
$137,050
Fund Source

The City of Cold Spring is looking to retrofit 24 acres of existing development within a 138 acre subcatchment of the City to improve the water quality of Cold Spring Creek, a designated trout stream. The large amounts of hard surfaces within the subcatchment area do not allow for rainfall or snow melt to soak into the ground. The stormwater carries with it sediment, bacteria, automotive fluids, and other pollutants. Cold Spring staff has frequently witnessed sediment plumes, the color of chocolate milk, at the storm sewer outfalls.

Stearns
Recipient
Anoka CD
2014 Fiscal Year Funding Amount
$42,987
Fund Source

This project will install new stormwater treatment practices in neighborhoods directly draining to Coon Lake. The objective is to remove phosphorus, which fuels algae growth, before the water is discharged into the lake. Seventeen potential project sites have been identified and ranked and include curb-cut rain gardens, swales, stabilizing stormwater discharge points, and a basin outlet modification.

Anoka
Recipient
Chisago SWCD
2014 Fiscal Year Funding Amount
$117,000
Fund Source

In 2011, the Chisago Soil and Water Conservation District (SWCD) received a Clean Water Fund (CWF) grant to inventory active gully erosion sites along the St. Croix River from the Wild River State Park entrance south to the Chisago/Washington county line. This inventory is now being used to contact landowners with active and severe gully erosion to begin the process of developing a plan correct the problems using Best Management Practices (BMPs).

Chisago
Recipient
Pine SWCD
2015 Fiscal Year Funding Amount
$63,400
Fund Source

This project will address impairments in the St. Croix, Kettle and Snake River Watersheds by reducing sediment and phosphorus delivery by encouraging private forest landowners within the St. Croix River Watershed in Pine County to re-establish riparian forest buffers, maintain existing riparian buffers and plant de-forested areas. It will develop a forest stewardship program and write forest stewardship plans in watersheds with the highest risk of impacts on water quality as listed by the Minnesota Forest Resources Council. This project will implement measures to achieve the St.

Pine
Recipient
Pine SWCD
2015 Fiscal Year Funding Amount
$48,800
Fund Source

This project will improve water quality, reducing phosphorus annually by 1,842 in the St. Croix, Kettle and Snake River Watersheds in Pine County by establishing cover crops to reduce erosion and phosphorus/fertilizer applications, increase soil fertility, permeability, and microbe activity. A no-till drill will be purchased for use by agricultural producers for installing cover crops as a means of decreasing soil erosion, reducing phosphorus and fertilizer applications and increasing soil health.

Pine
Recipient
Randy S. Ferrin
2011 Fiscal Year Funding Amount
$4,997
Fund Source

The Contractor will assist in planning and executing the regular meetings of the St. Croix River Basin Team, including providing minutes of the meetings. Assist in the functioning of the priority issue subcommittees. Respond to public notices for re-issuances of NPDES permits, EAWs and other pertinent public notices, and participate in prioritized public meetings with local governmental units and water planning organizations.

Anoka
Chisago
Isanti
Pine
Ramsey
Washington
Recipient
Tetra Tech
2017 Fiscal Year Funding Amount
$80,038
Fund Source

This project will conduct a 2017 revision of the South Fork Crow River, North Fork Crow River and Sauk River Watershed Hydrological Simulation Program FORTRAN (HSPF) models and review of the Pine River Watershed HSPF model.

Aitkin
Carver
Cass
Crow Wing
Douglas
Hennepin
Hubbard
Kandiyohi
McLeod
Meeker
Pope
Renville
Sibley
Stearns
Todd
Wright
Recipient
Chisago County
2012 Fiscal Year Funding Amount
$5,651
Fund Source

Chisago County will coordinate up to three community dialogue meetings to inform its water planning decisions. The goal of the meetings will be to provide safe, productive and effective venues for citizens to become authentically engaged in the water planning process. The outcome of this Civic engagement work with Chisago County and their county water planning process will be a more engaged public in the County Water Planning Process.

Anoka
Chisago
Isanti
Pine
Ramsey
Washington
Recipient
Chisago Soil and Water Conservation District
2012 Fiscal Year Funding Amount
$196,079
Fund Source

This project will support the necessary activities for improving the water quality and biological community by reducing nutrients, sediment levels and managing in-stream habitat within the Goose Creek 10-digit HUC Watershed. This restoration and protection plan will identify pollutant load reduction estimates and management strategies that will be used to obtain the TMDL goals outlined in the plan.

Anoka
Chisago
Isanti
Pine
Ramsey
Washington
Recipient
RESPEC
2012 Fiscal Year Funding Amount
$49,996
Fund Source

This project will finalize HSPF watershed model construction by incorporating internal phosphorus loading in modeled lakes, run a suite of implementation scenarios and generate a GenScn project containing model output. The consultant will produce HSPF watershed models that can readily be used to provide information to support conventional parameter TMDLs. The consultant will deliver all modeling files for baseline and implementation scenarios and provide a GenScn project containing model output.

Becker
Carver
Cass
Clearwater
Crow Wing
Douglas
Hennepin
Hubbard
Kandiyohi
McLeod
Meeker
Morrison
Otter Tail
Pope
Renville
Sibley
Stearns
Todd
Wadena
Wright
Recipient
Chisago County Soil & Water Conservation District
2013 Fiscal Year Funding Amount
$38,853
Fund Source

This project will support the development of whole farm conservation plans for ten (10) agricultural producers within the Sunrise River Watershed. The conservation plans will be used by the farmer and the Chisago SWCD to develop an action plan to address the resource concerns identified as part of the AgEQA program. The overall goal of the program is to prioritize conservation practices that will improve the overall water quality of the Sunrise River.

Anoka
Chisago
Isanti
Washington
Recipient
Barr Engineering
2013 Fiscal Year Funding Amount
$94,683
Fund Source

This project will complete a Watershed Restoration and Protection Plan for the Lower St. Croix River that provides quantitative pollutant load reduction estimates and a set of pollutant reduction and watershed management strategies to achieve water quality standards for all impairments within the watershed, and that are understood and adoptable by local units of government and other stakeholders.

Anoka
Chisago
Isanti
Pine
Ramsey
Washington
Recipient
Emmons & Olivier Resources
2013 Fiscal Year Funding Amount
$99,355
Fund Source

This project will complete a pollutant source identification and subwatershed information report and support the development of a Draft Restoration and Protection Plan (RAPP). It will also support the devlopment of a Implementation Plan that will identify target areas for BMP implementation for bacteria reductions.

Anoka
Benton
Carver
Crow Wing
Dakota
Douglas
Hennepin
Kandiyohi
McLeod
Meeker
Mille Lacs
Morrison
Pope
Ramsey
Sherburne
Sibley
Stearns
Todd
Washington
Wright
Recipient
Wenck Associates, Inc.
2013 Fiscal Year Funding Amount
$1,879
Fund Source

This project will support the completion of a final draft Total Maximum Daily Load (TMDL) document for the Osakis, Smith and Faille Lakes TMDL and the submittal to EPA for final approval.

Douglas
Meeker
Morrison
Pope
Stearns
Todd
Recipient
Kanabec Soil and Water Conservation District
2013 Fiscal Year Funding Amount
$31,398
Fund Source

This project will develop and organize a first- stage civic infrastructure pilot in Kanabec County, within the membership of the PICKM (Pine, Isanti, Chisago, Kanabec, and Mille-Lacs) Alliance, and with other organizations in the St. Croix Basin. The work will be grounded in the need for sustainable citizen engagement in water quality management. Civic leaders participating in this project will build their own skills for organizing people and working in partnership with Kanabec County SWCD staff and the St. Croix Basin Team to achieve water quality goals.

Chisago
Isanti
Kanabec
Mille Lacs
Pine
Recipient
Chisago Soil and Water Conservation District
2010 Fiscal Year Funding Amount
$196,600
Fund Source

TMDL project in the Chisago Lakes Lake Improvement District that will develop a watershed based plan and provide strategies for water quality and aquatic ecosystem management, restoration, and protection within Sunrise River Watershed. This project will also aid in understanding the Phosphorus loading to Lake St. Croix.

Anoka
Chisago
Isanti
Pine
Washington